How long does it take to build a kit plane? What 511,000 build log entries show

A typical kit plane flies after 1,630 logged hours over 4.4 years. What 511,000 entries from 5,000 public build logs show about pace and finishing.

Orange and blue gradient with the title KitFlight study on web-based builder logs, 2002 to 2026: 511,000 log entries from MyKitLog and the EAA Builders Log
5kpublic projects
0.5Mlog entries
1.9Mhours logged
1.4Mprogress photos

Twenty Years of Public Build Logs

Online build logs took off in the mid-2000s, the same years Van's RV-7 and RV-9 kits were shipping by the hundred. Builders used them to record hours and photos, and later to show the inspector their work at the airworthiness inspection.

On MyKitLog, entries peaked in 2009 and active builders in 2012, then declined steadily. The EAA Builders Log launched in 2019 and overtook MyKitLog in its first year. It grew fast through the pandemic years, peaked in 2023, and has slipped a little since: by 2025 it had about 6% fewer active builders than at its peak. Public web logging as a whole has stopped growing.

The two big sites aren't the whole picture anymore. In 2025 and 2026, AI tools made it easy to build a web app, and new web logs appeared: personal sites builders made for their own airplanes, some of them later opened to other builders as subscription services. Few of them publish numbers, so the hatched part of the bars is a rough estimate.

Fig. 1Public Web Build-Log Activity by Year
MyKitLogEAA Builders LogOther web tools (estimate)

A build log has to last longer than the build, and keeping a public website running that long has become harder. Sites disappear: Pew Research Center found that 38% of web pages that existed in 2013 could no longer be reached ten years later. Shared infrastructure fails too. Since October 2025, an Amazon Web Services outage disrupted customer applications for more than half a day, a Cloudflare failure left many of the websites on its network unreachable for hours, and a power failure in Google Cloud's London region disrupted services used by UK banks and Royal Mail for about six hours. In November 2026, Microsoft 365, including Outlook and Teams, was down from Thursday until Saturday. AI has also made attacks cheaper: Anthropic reported in 2025 that criminals with few technical skills were using AI to build ransomware and run operations that used to take years of training. A small build-log site, often run by one person, has the least money and time to keep up with all of this. A log whose main copy lives on the builder's own devices doesn't depend on any website staying up.

Supply problems show up in the logs too, and they show how long the kit industry takes to recover from a shock. Before 2019, fewer than 2 entries in 1,000 mentioned waiting for parts: a backordered part, an out-of-stock item, a kit that should have arrived by now. In 2020 it was about 1 in 120, and from 2021 to 2023 about 1 in 60. It eased in 2024, but in 2025 it was still about 1 in 90.

Van's builders felt it most. When Van's filed for Chapter 11 reorganization in December 2023, the company pointed to supply chain problems during COVID and to laser-cut parts made in response to high demand. In the logs, the share of Van's entries about waiting stayed above 2% from 2021 to 2023, peaking at 2.4% in 2023, and has come down since, to 1.5% in 2025, still more than ten times the level before 2019. Zenith's share peaked earlier, at 1.3% in 2021, and has stayed around 0.6%. For other kit makers it peaked at 1.3% in 2022 and was about 1% in 2025. Six years after the jump in 2020, none of the three groups is back to where it was before 2019.

Fig. 2Share of Log Entries That Mention Waiting for Parts, by Year

Kits and Models

About two in five projects are a Van's Aircraft RV, led by the four-seat RV-10, with the side-by-side RV-7 and the newer RV-14 tied for second. Most RV-14 logs are on the EAA site, which lifts it from eighth place to joint second. Zenith's CH 750 comes fourth, ahead of the tandem RV-8, and the CH 601/650, RANS and Sonex families make up most of the rest.

Fig. 3Projects by Aircraft Model
Van's RVOther kit makersCustom, undefined or other
Both sites combined.

Build Sessions

The typical MyKitLog entry covers 2.5 hours, and the typical EAA entry 3 hours. Most progress happens in frequent sittings of one to three hours. The small bumps at 8 and 10 hours are full shop days, which builders tend to log as round numbers.

Fig. 4How Long Is One Build Session?
MyKitLogEAA Builders Log12Median entryMiddle half of all entries
Share of each site's log entries by the hours logged in the entry, in one-hour bands. Each line adds up to 100%, so the two sites compare directly although MyKitLog has more entries.

When those sessions happen follows the working week. Saturday and Sunday together carry more than a third of all build hours. The seasons matter less than you might expect: January and March are the busiest months and July and December the quietest, but only by about a point.

If the weather drove the hobby, builders would slow down in summer and catch up in winter. Across all projects they hardly do: a builder who logs in a given month puts in about 25 to 28 hours, whatever the month. Switch to countries and the pattern stays mostly flat. Canadian builders log the most in January, about 30 hours, and less from August to October, about 24 to 26. Australians log the most in January, their midsummer, at about 32 hours.

Fig. 5Share of All Build Hours, by Weekday and Month
Is Building Seasonal? Hours a Builder Logs, by Month

Hours by Assembly

Most builders file entries under a section of the kit. Grouping their categories into the major assemblies shows the shape of an RV build: the wings and fuselage take about half the logged time between them, and the tail kit, the traditional first project, takes about a fifth.

Pick a model to compare it with the RV average. The RV-12 is the clearest outlier: about a third more of its time goes to the finishing kit and engine, and only half the usual share to wiring, thanks to its factory harness. Zenith builds split differently: the tail takes 11 to 12% of the logged hours, about half the RV share, and the low-wing CH 601/650 puts about a third of its time into the wings.

Fig. 6Average Share of Logged Hours by Assembly

Time to First Flight

Few logs say the build is done, but some record a first flight. We found 135 aircraft whose log records a first flight, with at least 300 hours logged before it.

The middle of that group logged about 1,630 hours over 4.4 years. The spread is wide. Quick-build kits and prior experience shorten a build, and some builders log more of their time than others.

Pace splits them almost evenly: about a third of these airplanes were built at under 5 hours a week, averaged from first entry to first flight, a third at 5 to 10, and a third at 10 or more. Slow builds finish too. They take longer on the calendar, which leaves more time to stop.

Fig. 7Logged Effort Before First Flight, One Dot per Aircraft
Van's RVOther kitsMyKitLogEAA Builders Log

Click a row to highlight its aircraft. Click a dot to open that airplane's build log.

Countries and States

Nine in ten public build logs come from the United States: 4,205 of the 4,594 projects with a known location, across both sites. Texas leads with 433 projects, then California, Florida, Colorado and Washington. Canada is next with 135 projects, then Australia with 105. MyKitLog is the more international of the two sites: nearly a fifth of its projects are outside the U.S., against one in twenty on the EAA Builders Log, where Canada outnumbers Australia.

Fig. 8Projects by U.S. State and by Country
MyKitLog and EAA Builders Log projects, airplanes on both sites counted once. MyKitLog: the location builders give on their project page. EAA Builders Log: the site's project map, usually the home airport or EAA chapter; projects placed only at a country's centre count for the country but no state. Countries with fewer than 5 projects, and MyKitLog countries we couldn't read, are in Other countries.

How Does Your Build Compare?

Set your own pace below. We'll place you among the 918 MyKitLog builders with at least 20 logging days, and project a first-flight date using the hours real builders logged to get there.

Fig. 9Your Pace Compared With Other Builders

A normal week when you do get to the shop.

Holidays, busy months at work and waiting on parts are weeks off.

Your average

—

Keeping a Build Moving

The 135 airplanes in our data that reached first flight logged a median of 1,630 hours over 4.4 years, and the middle half needed between 1,100 and 2,260 hours. At 5 hours a week, 1,630 hours takes about 6.3 years. At 10 hours a week, about 3.1.

Stopping is a bigger risk than building slowly. Half of all build logs go quiet within about 2 years, and many of those projects never fly. The builders who finish are not always the fastest. Most log two- or three-hour sessions most weeks, with more hours on weekends (Fig. 4 and Fig. 5).

A few habits keep a build moving:

  • Plan short, regular sessions instead of waiting for a free weekend. Two hours on a Tuesday counts.
  • Log every session the same day, with photos, while you still remember which rivets you skipped and why.
  • Track your average week. Weeks off count. Use the calculator above with honest numbers.
  • Keep the log where you'll actually open it, which in the hangar usually means your phone.

Choosing Where to Keep a Build Log

A build that takes five years needs a log that lasts longer: through the build, the airworthiness inspection and the years of flying after. The FAA's amateur-built guidance, Advisory Circular 20-27G, judges whether you did the major portion of the work, and your records are how you show it. EAA points out there's no official format for a builder's log, so choosing one is up to you.

For twenty years the default answer was a website. Our data suggests it was a poor fit. Both big public web logs have stopped growing: by 2025, MyKitLog had 89% fewer active builders than at its 2012 peak, and the EAA Builders Log about 6% fewer than in 2023 (Fig. 1). Fewer of the builders who sign up actually log, too: on the EAA site, 45% of projects started in 2026 had no entries by mid-November, against 12% of 2024 projects at the same point in their year. The reasons a website struggles in the shop are easy to see:

  • The work happens away from a desk. A web log asks you to sit down at a computer after the session, when the details have already faded.
  • Hangars are often offline. A web log needs a connection.
  • Photos take a detour. They're shot on a phone, then moved to a computer and uploaded through a form.
  • Someone else has to keep the site running, and secure, for longer than your build lasts.
  • Logs stall. On both sites, half of all logs went quiet within about 2 years.

Whatever you choose, ask:

  • Can you export everything, and what can you do with the files?
  • Who holds the data, and where is it stored?
  • Will it still open in ten years?
  • What happens if you stop paying the subscription?
  • Are you locked in?

Local-First Software

Software is swinging back toward owning your data. Local-first software, an idea set out in a widely cited 2019 essay by researchers at Ink & Switch and the University of Cambridge, keeps your data on your own devices first and uses the cloud for sync and backup.

KitFlight is built that way. Your logs live on your iPhone and iPad and sync through your own iCloud, with no KitFlight server holding your build. That is also why there is no subscription. Your project doesn't run on our servers, so it costs us nothing to keep, and there is no monthly storage bill to pass on to you. You pay once. KitFlight works fully offline and exports to PDF, CSV and JSON.

KitFlight runs on the phone because builders already carry one in the hangar, and more than nine in ten photos taken today are taken with a phone, according to Rise Above Research. Take a photo of the finished part and type or dictate a short update while the details are fresh.

Already logging on the EAA Builders Log or MyKitLog? KitFlight can import your log, with its entries, hours and photos. Download KitFlight on the App Store.

Quick Answers

How long does it take to build a kit plane?

In public build logs, a typical kit plane reached first flight after about 1,630 logged hours over 4.4 years (median of 135 aircraft). The middle half needed 1,100 to 2,260 hours. Logged hours are a floor: builders don't log everything.

How many hours does it take to build an RV-7 or RV-10?

RV-7 builds that logged a first flight recorded a median of 1,600 hours (18 aircraft). RV-10 builds recorded a median of 2,030 hours (11 aircraft). Quick-build kits and prior experience shorten both.

How long is a typical build session?

About 2.5 to 3 hours. Saturdays and Sundays carry 36% of all logged build hours.

Do I need a builder's log for an experimental aircraft?

The FAA needs to see that you did the major portion of the work (AC 20-27G), and a builder's log with photos is the usual way to show it. There is no official format.

What should I look for in a builder log?

Data you own and can keep without a subscription, full export (PDF, CSV, JSON) including photos, offline use in the hangar, and records that will still open long after the airplane flies.

About the data

  • Sources. MyKitLog: public project pages and work-log listings collected in May and July 2026, 1,354 projects with 244,045 log entries. EAA Builders Log: public projects collected using the site's text reports, one request at a time, in daily batches, in November 2026. All 3,385 public projects are included; private projects and private entries never are. EAA project locations come from the site's public project map.
  • Anonymization. Charts show aggregates. Names, usernames, cities and log text are not copied into this page. Every group shown (model, state, country) has at least 5 projects, except states, which are hatched below 3. Each dot in Fig. 7 is one aircraft with rounded numbers, linked to the public build log its builder published on MyKitLog or the EAA Builders Log.
  • Chart notes. Sessions (Fig. 4, Fig. 5) leave out entries over 24 hours and EAA logs written up weekly. Assemblies (Fig. 6) use projects with 300+ categorized hours, with builder categories matched by keyword. First flights (Fig. 7) use hours logged up to the first-flight entry; the Zenith row combines its models (10 aircraft, half of them CH 750s). States with 1 or 2 projects are hatched (Fig. 8).
  • Combining. 29 airplanes appeared on both sites. They were matched on model and their first three entries (dates and hours), not names, and counted once. EAA photo counts are capped at 100 per entry because a few entries report impossible numbers.
  • Cleaning. Manufacturer and model spellings were normalized ("Vans", "Van's Aircraft, Inc." and "VANS" are one maker; RV-7 and RV-7A are one model). Entries with more than 24 hours or impossible dates were dropped from time-based figures.
  • Limits. A build log is a voluntary record. Builders forget to log, log in batches, or stop logging after the airplane flies, so hours here are a floor: the true build time is longer.
  • Reuse. You may republish this article, its charts and its numbers, or use them as a source for your own analysis, as long as you include an active link to the original: https://www.kitflight.com/blog/how-long-to-build-a-kit-plane.